News
-
SALE OF USED EQUIPMENT
NOTICE
SALE OF USED EQUIPMENTNOTICE IS HEREBY GIVEN that the County of Burleigh, North Dakota will receive bids via online auction starting, September 23, 2026 until, October 6, 2026, for the sale of the following used equipment:
1. Unit 12-82 2007 Freightliner Columbia CL120 Semi Truck #1FUJA6CK27LY89449
2. Unit 12-83 2005 Freightliner Columbia CL120 Semi Truck #1FUJA6CK66PV76993
3. Unit 16-01 2004 Caterpillar Challenger MT535 Tractor #N170063
4. Unit 19-01 2010 Allianz/Global M3 Sweeper #2A9AM3H64AB181059
5. Unit 18-70 1997 Clement Pup Trailer 10 YD #1C9DB12BOTM110523
6. Unit 18-71 1997 Clement Pup Trailer 10 YD #1C9DB12BOTM110524
7. Unit 18-72 1997 Clement Pup Trailer 10 YD #1C9DB12BOTM110522
8. Unit 15-25 2019 J.D.672GP Motor Grader # 1DW672GPKKF695477
Bidding will be conducted via online auction at https://www.govdeals.com/BurleighCountyND. Interested bidders will be required to register and agree to the terms and conditions of the online auction prior to bidding.
Additional information and equipment inspection (by appointment) is available by contacting Russ or Brooks at the Burleigh County Highway Department, 8100 43rd Ave NE, Bismarck, ND 58503 (701-204-7748). This equipment is “sold as is, where is”.
Successful bidders will receive a Notice of Award by email from GovDeals.com.
The County of Burleigh reserves the right to reject any and all bids, to waive technicalities or to accept such as may be determined to be in the best interest of the County.
BY ORDER OF THE BOARD OF COMMISSIONERS
BURLEIGH COUNTY, NORTH DAKOTA
This 10th of September, 2026
Mark Splonskowski
Burleigh County Auditor
-
Apple Creek Road Reopened & Apple Creek Bridge Update
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerSeptember 16, 2026
Apple Creek Road Reopened
Apple Creek Road between 66th St SE and 80th St SE will be reopened Wednesday, September 16, 2026 at 5:00 pm.
Click here to see a map of the road reopening.
Apple Creek Bridge Update
Beginning September 21, the existing bridge approximately ½ mile east of 80th Street SE will be removed and replaced with triple box culverts. A stream diversion will also be installed.
🚧 A detour will be required while the bridge is removed and the new culverts are installed. Access across Apple Creek will not be possible during this work.
The contractor anticipates completing the bridge project by October 23, weather permitting.
Click here to see a map of the area of construction and detour.
-
80th St NE Construction Near I-94 Bridge
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerSeptember 16, 2026
80th St NE Construction
Beginning Monday, September 21, 2026 at 7:00 am, the NDDOT & Central Specialties, Inc. will begin construction on 80th St NE near the I-94 Bridge and continue through the week. Construction will include an asphalt mill and overlay. Flaggers will be present to direct traffic. Please expect delays and plan accordingly.
Contact NDDOT Bismarck District Office at 701-328-6950 with any questions.
-
Apple Creek Road Update
NEWS RELEASE
FOR IMMEDIATE RELEASESeptember 8, 2026
APPLE CREEK ROAD UPDATE
APPLE CREEK ROAD PROJECT UPDATE
Work continues on Apple Creek Road, with several segments moving into the final stages of construction.
Current Work – 66th Street SE to 80th Street SE
- The final asphalt layer has been completed.
- Crews are working on the roadside slopes and will continue for approximately the next two weeks, weather permitting.
- Once complete, crews will add topsoil, seed and mulch the areas.
- The roadway will then be cleaned and striped before this segment opens to traffic.
Work Beginning September 14
- 66th Street SE area: Milling will begin the morning of September 14, followed by paving beginning September 15.
- 80th Street SE area: Milling will begin the afternoon of September 14, followed by paving after the adjacent segment is completed.
- 80th Street SE to County Road 10: Milling and paving will follow the completion of the above work.
- Traffic impacts: Flaggers and a pilot car will be used during milling and paving operations. Please expect delays and allow extra time when traveling through the work zone.
- Click here to see a map of the construction areas.
Apple Creek Bridge
Beginning September 21, the existing bridge approximately ½ mile east of 80th Street SE will be removed and replaced with triple box culverts. A stream diversion will also be installed.🚧 A detour will be required while the bridge is removed and the new culverts are installed. Access across Apple Creek will not be possible during this work.
Click here to see a map of the bridge closure and detour.
The contractor anticipates completing the bridge project by October 23, weather permitting.
Questions?
Contact Casey Einrem at the Burleigh County Highway Department at (701) 204-7748.CASEY EINREM, PE
-
Apple Creek Rd & 80th St SE Construction
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerAugust 26, 2026
Apple Creek Rd & 80th St SE Construction
Beginning Monday, August 31, 2026 at 7:00 am, construction will be done on Apple Creek Road and 80th St SE in three segments. First segment: Apple Creek Rd starting at the intersection of 66th St SE and continue to the west approximately 1,300 feet. Second segment: Apple Creek Rd starting at 80th St SE and continue to the east to the Apple Creek bridge. Third segment: 80th St SE between Highway 10 and Apple Creek Rd. Construction will include a mill and overlay. Flaggers and pilot cars will be in place throughout construction. Anticipated project completion date is September 18, 2026, weather dependent. Please expect delays and plan accordingly.
Click here to view a map of the construction area.
Update: Apple Creek Rd between 66th St SE and 80th SE remains closed until construction is complete. The top lift of asphalt will begin Monday, August 31, 2026. Crews will continue to add side-slope material and topsoil along both sides of the roadway once the top lift of asphalt is finished. A signed detour remains in place. Thank you for your continued patience!
-
Morton Township Road Construction
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerAugust 3, 2026
Morton Township Construction
Beginning Monday, August 10, 2026 at 7:00 am, construction will begin in Morton Township. Construction will include culvert extensions and graveling of roadways. Flaggers will be present throughout construction. Anticipated project completion date is August 28, 2026, weather dependent. Please expect delays and plan accordingly. Click here to see a map showing the area of construction.
-
Moffit Road Construction
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerAugust 3, 2026
Moffit Road Construction
Beginning Monday, August 10, 2026 at 7:00 am, construction will begin on Moffit Road between 158th St SE and Highway 83. Construction will include a mill, overlay and chip seal. Pilot cars will be in place throughout construction. Anticipated project completion date is September 15, 2026, weather dependent. Please expect delays and plan accordingly. Click here to see a map of the construction area.
-
Apple Creek Road Construction Update
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerAugust 3, 2026
Apple Creek Road Construction Update
Apple Creek Road between 66th St SE and 80th St SE remains closed due to extra repairs. Final grading has wrapped up and base-lift asphalt paving is scheduled to begin Tuesday, August 4th and is expected to be finished by the end of the day on August 5th (weather permitting). After the base layer is in place, crews will add side-slope material and topsoil along both sides of the roadway. The top lift of asphalt and chip seal are anticipated to be applied during the last week of August, again dependent on weather. Once final surfacing is complete, the roadway will be reopened to traffic. A signed detour remains in place. Thank you for your patience as we work to improve the area!
-
Upcoming Road Closure - Apple Creek Road
NEWS RELEASE
FOR IMMEDIATE RELEASEContact: Casey Einrem, PE
Assistant County EngineerJune 15, 2026
Apple Creek Road Construction
Beginning Monday, June 22, 2026 at 7:00 am, Apple Creek Road will be closed between 66th St SE and 80th St SE for road construction. Construction will include asphalt milling, cement treated base, and overlay. Apple Creek Rd will be closed to through traffic with access for local residents only. A signed detour will be in place for all through traffic. Projected completion date is July 3, 2026, weather dependent. Please expect delays and plan accordingly. Click here to see a map showing the area of construction and detour.
-
Burleigh County Mitigation Plan Receives Official Approval
Burleigh County and its participating communities (Lincoln, Regan, Wilton, and Wing) have received formal approval of the updated Burleigh County Multi-Hazard Mitigation Plan (MHMP) from the Federal Emergency Management Agency (FEMA) and the North Dakota Department of Emergency Services. The plan, led by Emergency Management Director Mary Senger, is approved for the five-year period of April 29, 2026, through April 28, 2031. It identifies key hazards, assesses risks, and outlines projects to help communities better prepare for, withstand, and recover from disasters.
Why the Plan Matters
The Multi-Hazard Mitigation Plan represents a proactive approach to reducing risk. Studies show that every $1 spent on pre-disaster mitigation saves society an average of $6 in future disaster costs. The plan helps prioritize limited resources, raises awareness of local risks, and identifies potential projects to build long-term community resilience.
Access to Grant Funding
An approved MHMP is a critical requirement for accessing multiple federal hazard mitigation grant programs which makes Burleigh County and its partner communities eligible for significant FEMA and state funding opportunities.
The full plan is available on the Burleigh County website: www.burleigh.gov/mitigation